There are currently several on-going projects from the city and local utilities that will impact traffic around campus for the first week of the semester. The work is weather dependent, so specific dates cannot be provided.
ML&P work in Providence Drive: the right-hand westbound lane from Spirit Dr. to Seawolf Dr. will continue to be closed into the week of the 28th. The right-hand eastbound lane from Spirit Dr. to UAA Dr. will be closed until the middle of the week of the 28th.
Municipality of Anchorage sidewalk addition on UAA Drive: MOA does not expect to complete their concrete work before Monday. Lane restrictions around this project will cause significant traffic impacts for southbound traffic and those accessing Alumni Drive from UAA Drive.
ML&P work at 36th and Old Seward: this intersection will experience a full closure this weekend. The intersection will reopen early Monday. Intermittent lane closures will persist during weekdays.
intro text
This blog is intended to provide easy access to information about maintenance and construction activities that are occurring around campus. Blog posts will primarily be focused on notices, outages, and disruptions; however, we will also include notable information about activities of interest to the campus community.
We encourage you to check back frequently! Please bookmark, subscribe to our RSS feed, or follow us by email (box on the right).
If you have any questions, please email us at: facilities@uaa.alaska.edu.
Saturday, August 26, 2017
Monday, August 21, 2017
ML&P Work Update: Single-lane, East-bound closure
Municipal Light and Power expects the west-bound closure of Providence Drive between Seawolf Drive and Spirit Drive to conclude prior to Saturday, August 26. ML&P could not provide an exact date, as much of the remaining work is weather dependent.
As soon as the west-bound lanes are open, ML&P will be conducting a single-lane closure of east-bound Providence Drive between Spirit Drive and UAA Drive. See the map below. This is not a complete closure of east-bound traffic. This single-lane closure is expected to last 7 days.
As soon as the west-bound lanes are open, ML&P will be conducting a single-lane closure of east-bound Providence Drive between Spirit Drive and UAA Drive. See the map below. This is not a complete closure of east-bound traffic. This single-lane closure is expected to last 7 days.
Tuesday, August 15, 2017
UPDATED ML&P Work Update: Closure Shifting West, Impacts to Seawolf Dr. Intersection
On Wednesday, August 16, Municipal Light and Power's closure of west-bound lanes of Providence Drive will shift. The closure will be between Seawolf Drive and Spirit Drive. East-bound lanes will be accessible.
On Saturday, August 19, ML&P's work will extend into the Seawolf Drive intersection. This will temporarily block access to campus via Seawolf Drive. Access will be maintained via Spirit Drive. This closure is expected to last several days.
On Saturday, August 19, ML&P's work will extend into the Seawolf Drive intersection. This will temporarily block access to campus via Seawolf Drive. Access will be maintained via Spirit Drive. This closure is expected to last several days.
Monday, August 14, 2017
ENSTAR Repairs by Templewood
On Wednesday, August 16th ENSTAR will begin repairs to the gas distribution line that runs in front of the Templewood housing units. This work is expected to take 1 week. Please be aware of equipment and crews working in this area.
Wednesday, August 9, 2017
Updated Pedestrian Detour for South Lot Repair Work
There has been a change to the pedestrian access route for EIB and ANSEP around the repair work in South Parking Lot. Due to adjacent utility work in Providence Drive the previously announced pedestrian detour route for access to EIB and ANSEP will be unavailable. Pedestrian access to the EIB and ANSEP will now be along Spirit Dr. See the map below.
Expect a significant presence of large truck traffic entering and leaving the South Lot as a result of the EIB walkway and parking lot project. Caution should be taken when walking to/from your vehicles in this area, especially when near the site fence access gates. Please do not enter or walk through the active construction area.
Expect a significant presence of large truck traffic entering and leaving the South Lot as a result of the EIB walkway and parking lot project. Caution should be taken when walking to/from your vehicles in this area, especially when near the site fence access gates. Please do not enter or walk through the active construction area.
Monday, August 7, 2017
ML&P Work Update: Impacts at Intersection of Providence Dr. and Spirit Dr.
On Thursday, August 10th, Municipal Light and Power's work will extend into the intersection at Spirit Drive. This will temporarily block access to campus via Spirit Drive. Access will be maintained via Seawolf Drive. This closure is expected to last several days.
East-bound thru-traffic will be able to use the intersection during this time
East-bound thru-traffic will be able to use the intersection during this time
Monday, July 31, 2017
South Lot and EIB Sidewalk Repairs, August 1 to August 25
On August 1 Neeser Construction will start repairs to the South Lot and sidewalk adjacent to the Engineering and Industry Building. They are expected to complete the work by August 25. See the map below for the anticipated impacts to the South Parking Lot and west EIB sidewalk.
The main entry to the EIB will be closed. Pedestrian traffic going to/from South Parking Lot will be directed to the sidewalk south of EIB. Additionally, the Pay-&-Park will be unavailable during this time.
The main entry to the EIB will be closed. Pedestrian traffic going to/from South Parking Lot will be directed to the sidewalk south of EIB. Additionally, the Pay-&-Park will be unavailable during this time.
Monday, July 17, 2017
ML&P Power Transfer
On Tuesday, July 18th, Municipal Light and Power will be transferring the electrical service for the following buildings:
Later this week - tentatively Thursday - this work will be conducted again, but in reverse order, to transfer the load to the new equipment.
- WFSC, SU, Bookstore/GSS, ANSEP, EIB, ECB, NSB, Central Garage, and SSB.
Later this week - tentatively Thursday - this work will be conducted again, but in reverse order, to transfer the load to the new equipment.
Thursday, July 13, 2017
ML&P Work Update - Road Closure Shifting West
Beginning the weekend of July 15 UAA Drive will be closed between Alumni Drive and Providence Drive. In addition, the west-bound lanes of Providence Drive will be closed between Spirit Drive and Alumni Drive. See the map below. The intersection and west-bound lanes between UAA Drive and Alumni Drive will reopen the morning of July 17.
From July 17 to August 7 the west-bound lanes of Providence Drive between Spirit Drive and UAA Drive will be closed.
East-bound lanes will remain open. UAA's internal detour route is Alumni Drive and Mallard Lane.
From July 17 to August 7 the west-bound lanes of Providence Drive between Spirit Drive and UAA Drive will be closed.
East-bound lanes will remain open. UAA's internal detour route is Alumni Drive and Mallard Lane.
Wednesday, July 5, 2017
UPDATE: Partial Closure of Seawolf Drive
Starting Monday, July 10 Seawolf Drive will experience a partial closure. This is to conduct repairs on a failed fire hydrant next to the Rasmuson Hall. Traffic will detour through the Sports Center West Lot. Due to the detour traffic parking will not be available in the Sports Center West Lot.
This project was previously announced for June 23. Circumstances forced a delay in the schedule.
This project was previously announced for June 23. Circumstances forced a delay in the schedule.
Subscribe to:
Posts (Atom)