intro text

This blog is intended to provide easy access to information about maintenance and construction activities that are occurring around campus. Blog posts will primarily be focused on notices, outages, and disruptions; however, we will also include notable information about activities of interest to the campus community.

We encourage you to check back frequently! Please bookmark, subscribe to our RSS feed, or follow us by email (box on the right).

If you have any questions, please email us at: facilities@uaa.alaska.edu.

Friday, October 6, 2017

ENSTAR Activites Along Providence Drive, Pathway Impacts

Starting Monday, October 9 and continuing through Saturday, October 14 ENSTAR Natural Gas will be conducting work on the north-side of Providence Drive. This work will impact the multi-use pathway. See the maps below for areas of impact and detour routes.

Please be aware of construction personnel and equipment operating in and around these areas.



Monday, September 11, 2017

Central Garage Closure, September 15-26

Starting Friday, September 15 and continuing through Tuesday, September 26, the Central Garage will be closed to all parking. This closure is to facilitate repairs to drain lines within the garage. This past winter the drains frequently backed up, creating large areas of ice. This resulted in unsafe conditions for vehicles and pedestrians. These repairs will address this issue. The East Garage and Engineering Garage will continue to be available during this time, as will the surface lot in front of Central Garage.

Thank you for your understanding.
For questions, please call Parking Services: 786-1119


Tuesday, September 5, 2017

Update Regarding Municipality's UAA Drive Sidewalk Project

This summer the Municipality of Anchorage began a project to add a sidewalk along the west-side of UAA Drive. The sidewalk runs from Mallard Lane to the existing sidewalk next to ECB. The Municipality intended to have the project completed before the start of the semester. They were unable to meet that goal. UAA Facilities has received numerous inquiries about the schedule of this project and when the traffic diversion on UAA Drive will end.

As of 9/5/17 the Municipality reported some rework required on the sidewalk that was installed last week. They expect to address the issue this week, with the intention of returning to the normal traffic pattern by the week of September 11. The work is weather dependent, so there is a chance their schedule will push out again.

Saturday, August 26, 2017

City and Utility Project Updates, Traffic Impacts for First Week of Classes

There are currently several on-going projects from the city and local utilities that will impact traffic around campus for the first week of the semester. The work is weather dependent, so specific dates cannot be provided.

ML&P work in Providence Drive: the right-hand westbound lane from Spirit Dr. to Seawolf Dr. will continue to be closed into the week of the 28th. The right-hand eastbound lane from Spirit Dr. to UAA Dr. will be closed until the middle of the week of the 28th.

Municipality of Anchorage sidewalk addition on UAA Drive: MOA does not expect to complete their concrete work before Monday. Lane restrictions around this project will cause significant traffic impacts for southbound traffic and those accessing Alumni Drive from UAA Drive.

ML&P work at 36th and Old Seward: this intersection will experience a full closure this weekend. The intersection will reopen early Monday. Intermittent lane closures will persist during weekdays.

Monday, August 21, 2017

ML&P Work Update: Single-lane, East-bound closure

Municipal Light and Power expects the west-bound closure of Providence Drive between Seawolf Drive and Spirit Drive to conclude prior to Saturday, August 26. ML&P could not provide an exact date, as much of the remaining work is weather dependent.

As soon as the west-bound lanes are open, ML&P will be conducting a single-lane closure of east-bound Providence Drive between Spirit Drive and UAA Drive. See the map below. This is not a complete closure of east-bound traffic. This single-lane closure is expected to last 7 days.


Tuesday, August 15, 2017

UPDATED ML&P Work Update: Closure Shifting West, Impacts to Seawolf Dr. Intersection

On Wednesday, August 16, Municipal Light and Power's closure of west-bound lanes of Providence Drive will shift. The closure will be between Seawolf Drive and Spirit Drive. East-bound lanes will be accessible.

On Saturday, August 19, ML&P's work will extend into the Seawolf Drive intersection. This will temporarily block access to campus via Seawolf Drive. Access will be maintained via Spirit Drive. This closure is expected to last several days.


Monday, August 14, 2017

ENSTAR Repairs by Templewood

On Wednesday, August 16th ENSTAR will begin repairs to the gas distribution line that runs in front of the Templewood housing units. This work is expected to take 1 week. Please be aware of equipment and crews working in this area.

Wednesday, August 9, 2017

Updated Pedestrian Detour for South Lot Repair Work

There has been a change to the pedestrian access route for EIB and ANSEP around the repair work in South Parking Lot. Due to adjacent utility work in Providence Drive the previously announced pedestrian detour route for access to EIB and ANSEP will be unavailable. Pedestrian access to the EIB and ANSEP will now be along Spirit Dr. See the map below.

Expect a significant presence of large truck traffic entering and leaving the South Lot as a result of the EIB walkway and parking lot project. Caution should be taken when walking to/from your vehicles in this area, especially when near the site fence access gates. Please do not enter or walk through the active construction area.



Monday, August 7, 2017

ML&P Work Update: Impacts at Intersection of Providence Dr. and Spirit Dr.

On Thursday, August 10th, Municipal Light and Power's work will extend into the intersection at Spirit Drive. This will temporarily block access to campus via Spirit Drive. Access will be maintained via Seawolf Drive. This closure is expected to last several days.

East-bound thru-traffic will be able to use the intersection during this time


Monday, July 31, 2017

South Lot and EIB Sidewalk Repairs, August 1 to August 25

On August 1 Neeser Construction will start repairs to the South Lot and sidewalk adjacent to the Engineering and Industry Building. They are expected to complete the work by August 25. See the map below for the anticipated impacts to the South Parking Lot and west EIB sidewalk.

The main entry to the EIB will be closed. Pedestrian traffic going to/from South Parking Lot will be directed to the sidewalk south of EIB. Additionally, the Pay-&-Park will be unavailable during this time.