UAA Winter Break Construction Maps
intro text
Thursday, December 28, 2023
Wednesday, April 26, 2023
Friday, December 16, 2022
2022/2023 Winter Break Construction Projects - Descriptions
The following is a list of project activities lead by Facilities Planning & Construction scheduled to have work occurring during the 2022/2023 campus winter break.
Professional Studies Building
·
Project Number & Name: 20-0128 West Campus
Earthquake Repairs
o
Project Manager: Christopher Wolpert
o
Contractor: West Coast Concrete Restoration
o
Project Scope: Demolition of ACM containing
ceiling tile, ceiling grid repair, and re-installation of ceiling tile.
Gordon
Hartlieb Hall
·
Project Number & Name: A23037 GHH
Facilities Renovation
o
Project Manager: Heather Tribble & Eric
Lopez
o
Contractor: World Wide Movers & TBD (Minor
Construction Support)
o
Project Scope: Relocation of CAFÉ staff from
GHH to the Library, minor space modifications.
·
Project Number & Name: 21-0004 GHH
Mechanical Improvements
o
Project Manager: Andi McKinzie
o
Contractor: KC General Contractors &
Subcontractors
o
Project Scope: Final mechanical work with a
focus on the welding & ceramic lab spaces.
Eugene
Short Hall
·
Project Number & Name: A23002
Communications Faculty Relocation from ESH to SSB
o
Project Manager: Eric Lopez
o
Contractor: World Wide Movers with Maintenance
Support
o
Project Scope: Relocation of team members from
ESH to SSB
Rasmuson
Hall
·
Project Number & Name: A23016 ISER
Relocation from BOC3
o
Project Manager: Eric Lopez
o
Contractor: World Wide Movers
o
Project Scope: Relocation of team members from
BOC3 to RH
Seawolf
Sports Complex
·
Project Number & Name: 20-0061 Arch Flash
Upgrades
o
Project Manager: Andi McKinzie
o
Contractor: Vannoy Electric
o
Project Scope: Tentative, listed for
situational awareness, code required electrical upgrades that will impact
building power for 4 to 6 hours, parts currently not in-town
·
Project Number & Name: A22130 Gym Floor
Refinish
o
Project Manager: Eric Lopez
o
Contractor: Alaskan Industries
o
Project Scope: Refinish of the gymnasium floor
Engineering
& Computation Building
·
Project Number & Name: A23022 ECB Atrium
Stairs
o
Project Manager: Cory Fischer
o
Contractor: Eastside Carpet
o
Project Scope: Demolition and installation of
stair treads
Native
Arts Studio
·
Project Number & Name: A23030 Native Arts
Studio Relocation
o
Project Manager: Cory Fischer & Eric Lopez
o
Contractor: TBD
o
Project Scope: Relocation of equipment and
material from the portable building into the Fine Arts Building
Social
Sciences Building
·
Project Number & Name: 20-0125
Central-East Earthquake Repairs
o
Project Manager: Christopher Wolpert &
Jennifer Smith
o
Contractor: Drennon Construction &
Consultant
o
Project Scope: Patch & paint, ceiling grid
repairs, and other incidental work as a final completion of the recovery from
the 2018 Cook Inlet Earthquake
·
Project Number & Name: A23002
Communications Faculty Relocation from ESH to SSB
o
Project Manager: Eric Lopez
o
Contractor: World Wide Movers with Maintenance
Support
o
Project Scope: Relocation of team members from
ESH to SSB
Consortium
Library
·
Project Number & Name: 20-0125
Central-East Earthquake Repairs
o
Project Manager: Christopher Wolpert &
Jennifer Smith
o
Contractor: Drennon Construction &
Consultant
o
Project Scope: Patch & paint, ceiling grid
repairs, and other incidental work as a final completion of the recovery from
the 2018 Cook Inlet Earthquake
·
Project Number & Name: 21-0004 GHH
Mechanical Improvements
o
Project Manager: Andi McKinzie
o
Contractor: KC General Contractors &
Subcontractors
o
Project Scope: Final mechanical work with a
focus on the welding & ceramic lab spaces.
Administration
Building
·
Project Number & Name: 20-0125
Central-East Earthquake Repairs
o
Project Manager: Christopher Wolpert &
Jennifer Smith
o
Contractor: Drennon Construction &
Consultant
o
Project Scope: Patch & paint, ceiling grid
repairs, and other incidental work as a final completion of the recovery from
the 2018 Cook Inlet Earthquake
Fine
Arts Building
·
Project Number & Name: 20-0125 Central-East
Earthquake Repairs
o
Project Manager: Christopher Wolpert &
Jennifer Smith
o
Contractor: Drennon Construction &
Consultant
o
Project Scope: Patch & paint, ceiling grid
repairs, and other incidental work as a final completion of the recovery from
the 2018 Cook Inlet Earthquake
·
Project Number & Name: A23030 Native Arts
Studio Relocation
o
Project Manager: Cory Fischer & Eric Lopez
o
Contractor: TBD
o
Project Scope: Relocation of equipment and
material from the portable building into the Fine Arts Building
East
Hall
·
Project Number & Name: 21-0030 EASTH
Elevator Modernization
o
Project Manager: Heather Tribble
o
Contractor: Otis Elevator
o Project Scope: Preliminary work to elevator cab in order to begin work required to modernize and return the elevator into operation
University
Center
·
Project Number & Name: 21-0015 Mechanical
Upgrades
o
Project Manager: Christopher Wolpert
o
Contractor: Klebs Mechanical
o
Project Scope: Final close out work in the
field in order to complete the project
Bragaw
Office Complex
·
Project Number & Name: 20-0027 Window Well
& North Entry
o
Project Manager: Cory Fischer & Eric Lopez
o
Contractor:
CYS Enterprises, LLC
o
Project Scope: North entry modifications to
repair rusted decking and mitigate water intrusion.
·
Project Number & Name: 20-0061 Arch Flash
Upgrades
o
Project Manager: Andi McKinzie
o
Contractor: Vannoy Electric
o
Project Scope: Code required electrical
upgrades that will impact building power for 4 to 6 hours
·
Project Number & Name: A23016 ISER
Relocation from BOC3
o
Project Manager: Eric Lopez
o
Contractor: World Wide Movers
o
Project Scope: Relocation of team members from
BOC3 to RH
Matanuska-Susitna
Campus
·
Project Number & Name: 18-0012 Diesel Fire
Pump Replacement
o
Project Manager: Chris Wolpert
o
Contractor: JGH Plumbing & Heating
o Project Scope: Installation of the new fire pump, all other work is substantially complete
Thursday, April 7, 2022
Tuesday, July 30, 2019
ENSTAR Work Along Alumni Drive
Wednesday, July 24, 2019
ENSTAR: Partial Closures of Spirit Drive
On Saturday, July 27 - Spirit Drive will be closed at Seawolf Drive. This is a one-day closure. South Lot, Seawolf Sports Complex, Student Union, Bookstore, and Engineering and Industry Buildings will all remain accessible via the Providence Drive and Spirit Intersection. See the graphic below for more detail.
Beginning Monday, July 29 - ENSTAR will begin trenching along the length of Spirit Drive. This work will close the west-bound lane. The east-bound lane will remain open. ENSTAR will conduct this work in sections, so pedestrian access from South Lot to the buildings will be maintained. South Lot, Seawolf Sports Complex, Student Union, Bookstore, and Engineering and Industry Buildings will all remain accessible via the Seawolf Drive and Spirit Intersection. See the graphic below for more detail. This portion of the work is expected to last one week.