The following is a list of project activities lead by Facilities Planning & Construction scheduled to have work occurring during the 2022/2023 campus winter break.
Professional Studies Building
·
Project Number & Name: 20-0128 West Campus
Earthquake Repairs
o
Project Manager: Christopher Wolpert
o
Contractor: West Coast Concrete Restoration
o
Project Scope: Demolition of ACM containing
ceiling tile, ceiling grid repair, and re-installation of ceiling tile.
Gordon
Hartlieb Hall
·
Project Number & Name: A23037 GHH
Facilities Renovation
o
Project Manager: Heather Tribble & Eric
Lopez
o
Contractor: World Wide Movers & TBD (Minor
Construction Support)
o
Project Scope: Relocation of CAFÉ staff from
GHH to the Library, minor space modifications.
·
Project Number & Name: 21-0004 GHH
Mechanical Improvements
o
Project Manager: Andi McKinzie
o
Contractor: KC General Contractors &
Subcontractors
o
Project Scope: Final mechanical work with a
focus on the welding & ceramic lab spaces.
Eugene
Short Hall
·
Project Number & Name: A23002
Communications Faculty Relocation from ESH to SSB
o
Project Manager: Eric Lopez
o
Contractor: World Wide Movers with Maintenance
Support
o
Project Scope: Relocation of team members from
ESH to SSB
Rasmuson
Hall
·
Project Number & Name: A23016 ISER
Relocation from BOC3
o
Project Manager: Eric Lopez
o
Contractor: World Wide Movers
o
Project Scope: Relocation of team members from
BOC3 to RH
Seawolf
Sports Complex
·
Project Number & Name: 20-0061 Arch Flash
Upgrades
o
Project Manager: Andi McKinzie
o
Contractor: Vannoy Electric
o
Project Scope: Tentative, listed for
situational awareness, code required electrical upgrades that will impact
building power for 4 to 6 hours, parts currently not in-town
·
Project Number & Name: A22130 Gym Floor
Refinish
o
Project Manager: Eric Lopez
o
Contractor: Alaskan Industries
o
Project Scope: Refinish of the gymnasium floor
Engineering
& Computation Building
·
Project Number & Name: A23022 ECB Atrium
Stairs
o
Project Manager: Cory Fischer
o
Contractor: Eastside Carpet
o
Project Scope: Demolition and installation of
stair treads
Native
Arts Studio
·
Project Number & Name: A23030 Native Arts
Studio Relocation
o
Project Manager: Cory Fischer & Eric Lopez
o
Contractor: TBD
o
Project Scope: Relocation of equipment and
material from the portable building into the Fine Arts Building
Social
Sciences Building
·
Project Number & Name: 20-0125
Central-East Earthquake Repairs
o
Project Manager: Christopher Wolpert &
Jennifer Smith
o
Contractor: Drennon Construction &
Consultant
o
Project Scope: Patch & paint, ceiling grid
repairs, and other incidental work as a final completion of the recovery from
the 2018 Cook Inlet Earthquake
·
Project Number & Name: A23002
Communications Faculty Relocation from ESH to SSB
o
Project Manager: Eric Lopez
o
Contractor: World Wide Movers with Maintenance
Support
o
Project Scope: Relocation of team members from
ESH to SSB
Consortium
Library
·
Project Number & Name: 20-0125
Central-East Earthquake Repairs
o
Project Manager: Christopher Wolpert &
Jennifer Smith
o
Contractor: Drennon Construction &
Consultant
o
Project Scope: Patch & paint, ceiling grid
repairs, and other incidental work as a final completion of the recovery from
the 2018 Cook Inlet Earthquake
·
Project Number & Name: 21-0004 GHH
Mechanical Improvements
o
Project Manager: Andi McKinzie
o
Contractor: KC General Contractors &
Subcontractors
o
Project Scope: Final mechanical work with a
focus on the welding & ceramic lab spaces.
Administration
Building
·
Project Number & Name: 20-0125
Central-East Earthquake Repairs
o
Project Manager: Christopher Wolpert &
Jennifer Smith
o
Contractor: Drennon Construction &
Consultant
o
Project Scope: Patch & paint, ceiling grid
repairs, and other incidental work as a final completion of the recovery from
the 2018 Cook Inlet Earthquake
Fine
Arts Building
·
Project Number & Name: 20-0125 Central-East
Earthquake Repairs
o
Project Manager: Christopher Wolpert &
Jennifer Smith
o
Contractor: Drennon Construction &
Consultant
o
Project Scope: Patch & paint, ceiling grid
repairs, and other incidental work as a final completion of the recovery from
the 2018 Cook Inlet Earthquake
·
Project Number & Name: A23030 Native Arts
Studio Relocation
o
Project Manager: Cory Fischer & Eric Lopez
o
Contractor: TBD
o
Project Scope: Relocation of equipment and
material from the portable building into the Fine Arts Building
East
Hall
·
Project Number & Name: 21-0030 EASTH
Elevator Modernization
o
Project Manager: Heather Tribble
o
Contractor: Otis Elevator
o Project Scope: Preliminary work to elevator cab in order to begin work required to modernize and return the elevator into operation
University
Center
·
Project Number & Name: 21-0015 Mechanical
Upgrades
o
Project Manager: Christopher Wolpert
o
Contractor: Klebs Mechanical
o
Project Scope: Final close out work in the
field in order to complete the project
Bragaw
Office Complex
·
Project Number & Name: 20-0027 Window Well
& North Entry
o
Project Manager: Cory Fischer & Eric Lopez
o
Contractor:
CYS Enterprises, LLC
o
Project Scope: North entry modifications to
repair rusted decking and mitigate water intrusion.
·
Project Number & Name: 20-0061 Arch Flash
Upgrades
o
Project Manager: Andi McKinzie
o
Contractor: Vannoy Electric
o
Project Scope: Code required electrical
upgrades that will impact building power for 4 to 6 hours
·
Project Number & Name: A23016 ISER
Relocation from BOC3
o
Project Manager: Eric Lopez
o
Contractor: World Wide Movers
o
Project Scope: Relocation of team members from
BOC3 to RH
Matanuska-Susitna
Campus
·
Project Number & Name: 18-0012 Diesel Fire
Pump Replacement
o
Project Manager: Chris Wolpert
o
Contractor: JGH Plumbing & Heating
o Project Scope: Installation of the new fire pump, all other work is substantially complete