The rough project timeline is:
- Toward the end of the week of April 7th: clearing along the west side of UAA Dr.
- Toward the end of April: construction in the roadway begins
- Toward the end of May: lane closures will begin
- October: project completion
Any hindrances to traffic flow will be restricted to evenings and weekends.
This is a DOT project funded by the federal Highway Safety Improvement Program, and not a UAA project. We will do our best to keep the campus community informed as this project progresses.
Click here for DOT's one-page handout on the project.
Click here for DOT's one-page handout on the project.