Starting at 6:00 pm Wednesday, September 24th Neeser Construction will begin this work. To make the temporary road functional some work has to be completed within UAA Drive. These activities will be conducted in the evenings, between 6:00 pm and 9:30 pm. Flaggers will be on site to regulate traffic through the area. It is expected that work within and along UAA Drive will be complete by October 15th.
Mallard Lane is expected to reopen on October 18th, pending any delays from weather or other sources.
This is a temporary road. It will be closed again as we approach Summer so that the permanent road can be constructed.