UAA Drive will be closed from south of Widgeon Lane to Alumni Drive (map below). The closures will be in effect between 8:00 p.m. Friday and 6:00 a.m. Monday for both weekends. The work will entail:
- August 8 & 9: installation of a storm drain across UAA Drive and Mallard Lane and construction of medians
- August 15 & 16: paving work around the UAA Drive and Mallard Lane intersection
The project team discussed trying to accomplish this work through individual lane closures; however, this would be impractical because of the nature of the work. Condensing the work to these two weekends allows Neeser to complete the work quickly and safely before the fall semester begins.