- 7/28 - 7/31: Electrical/mechanical demo of the old condensing unit.
- 7/31: Crane lifts old unit off the roof. The new unit is staged in the parking lot for prep-work.
- 8/3 - 8/10: New structural steel/rooftop stands for the new unit are installed.
- 8/11: Crane lifts the new unit onto the roof.
- 8/11 - 8/28: The new unit is tied into the building's systems.
Please pay attention to all safety flagging. We anticipate the days when the crane is onsite to only be 1/2 days, but during those periods the crane will be blocking the south entrance.